Date  
Title Hide Details 
7/23/10 > Construction Progress July 23, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending July 23rd, 2010

 

Construction activity that occurred this week:

 

§   Del City High School

a) Completed installation of decorative Fence.

b) Completed hydro mulch.

c) Completed Electrical Final walk-thru

 

§   Midwest City High School

a) Completing punchlist items.

b) Continue installation of retaining wall at west-end drainage.

c) Completed hydro mulch.

d) Delivery of decorative fence.

e) Completed Electrical Final walk-thru

 

§   Carl Albert High School

a) Completing punchlist items.

b) Completed chain-link fence installation.

c) Complete track striping.

d) Completed hydro mulch.

e) Delivery of decorative fence.

f) Completed Electrical Final walk-thru

 

We are anticipating construction activity for the following items next week:

 

§   Del City High School

a) Complete Security Camera Final walk-thru

b) Repair punchlist items

c) Removal of construction debris.

d) Demobilize

 

§   Midwest City High School

a) Complete Security Camera Final walk-thru

b) Complete retaining wall installation.

c) Complete punchlist items.

 

§   Carl Albert High School

a) Complete Security Camera Final walk-thru

b) Begin installation of decorative fence.

c) Complete punchlist items.

 

7/16/10 > Construction Progress July 16, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending July 16th, 2010

 

Construction activity that occurred this week:

 

§   Del City High School

a) Completed punchlist items.

b) Began installing decorative Fence.

 

§   Midwest City High School

a) Completing punchlist items.

b) Completed installation of chain-link fence.

c) Began installing retaining wall at west-end drainage.

 

§   Carl Albert High School

a) Completing punchlist items.

b) Continued chain-link fence installation.

c) Completed final-coating on track surface.

d) Complete final walk-thru of track.

e) Began track striping.

 

We are anticipating construction activity for the following items next week:

 

§   Del City High School

a) Hydro mulch.

b) Complete installation of Decorative fence.

 

§   Midwest City High School

a) Hydro mulch.

b) Delivery of decorative fence.

c) Complete retaining wall installation.

d) Complete punchlist items.

 

§   Carl Albert High School

a) Hydro mulch.

b) Complete track striping.

c) Complete chain-link fence installation.

d) Delivery & begin installation of decorative fence.

e) Complete punchlist items.

 

 

 

 

7/09/10 > Construction Progress July 9, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending July 9th, 2010

 

Construction activity that occurred this week:

 

§   Del City High School

a) Completing punchlist items.

b) Final grooming of turf.

c) Grooming equipment training.

 

§   Midwest City High School

a) Completing punchlist items.

b) Continued chain-link fence installation.

c) Final grooming of turf.

d) Grooming equipment training.

 

§   Carl Albert High School

a) Completing punchlist items.

b) Continued chain-link fence installation.

c) Grooming equipment training.

d) Rain has hampered the installation of final track coating.  This final coat is extremely water-sensitive.  The surface must be completely dry before installation; and no rain for a minimum of 2-hours after installation.

 

We are anticipating construction activity for the following items next week:

 

§   Del City High School

a) Hydro mulch.

b) Delivery of Decorative fence.

c) Complete punchlist items.

 

§   Midwest City High School

a) Hydro mulch.

b) Complete chain-link fence installation.

c) Begin installing retaining wall at west-end drainage.

d) Complete punchlist items.

 

§   Carl Albert High School

a) Hydro mulch.

b) Complete track surfacing.

c) Complete chain-link fence installation.

d) Final grooming of turf.

e) Complete punchlist items.

 

 

 

 

6/11/10 > Construction Progress June 11, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending June 11th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Complete installation of chainlink fencing.

 

§ Midwest City High School

a)   Continued fence installation.

b)   Completed installing turf material, and gluing strips together, gluing in hash marks, logos, and all field markings.  "Greened-Out"

c)   Began installing infill material into turf.

d)   Completed installation of security equipment.

 

§ Carl Albert High School

a)   Completed installing turf material, and gluing strips together, gluing in hash marks, and all field markings at the Practice Field.  "Greened-Out"

b)   Completed installing turf material, and gluing strips together, gluing in hash marks, logos, and all field markings at the Playing Field.  "Greened-Out"

c)   Completed installation of security equipment.

 

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School (remaining work to be completed)

a)   Hydro mulch.

b)   Install Decorative fence.

 

§ Midwest City High School

a)   Continue fence installation.

b)   Continue installing infill material into turf.

c)   Begin installing retaining wall at West end of track.

 

§ Carl Albert High School

a)   Coordinate start of track surfacing.

b)   Begin installing of chain-link fencing.

 

 

 

6/04/10 > Construction Progress June 4, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending June 4th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Completed track striping.

b)   Continued installation of chainlink fencing - 98% complete.

 

§ Midwest City High School

a)   Continued installing turf material, and gluing strips together, gluing in hash marks, logos, and all field markings.

b)   Continued installing security equipment.

 

§ Carl Albert High School

a)   Completed the subsurface drainage system at the practice field.

b)   Completed the rock base at the practice and playing fields.

c)   Completed perimeter grading and clean up at the practice and playing fields.

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Hydromulch.

b)   Complete installation of chainlink fencing with installing gates.

 

§ Midwest City High School

a)   Continue fence installation.

b)   Begin installing infill material into turf.

c)   Begin installing retaining wall at West end of track.

d)   Complete installation of security equipment.

 

§ Carl Albert High School

a)   Begin installing turf material at the practice field.

b)   Coordinate start of track surfacing.

 

5/28/10 > Construction Progress May 28, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending May 28, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Completed installation of security equipment.

b)   Continued fence installation.

c)   Performed initial punchlist, and turned field over to Del City High School.

d)   Poured concrete strip on visitor side.

e)   Poured misc. concrete.

 

§ Midwest City High School

a)   Continued installing security equipment.

b)   Installing turf material.

c)   Installing fence

d)   Completed track striping.

e)   Poured misc. concrete.

 

§ Carl Albert High School

a)   Completed the rock compaction for turf installation.

b)   Completed installation of security equipment.

c)   Installed asphalt for the track.

d)   Began installation of the subsurface drainage system at the practice field.

e)   Began installation of the rock base at the practice field.

f)   Poured concrete pads for discuss & shot put.

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Track striping.

b)   Continue fence installation.

c)   Hydromulch.

 

§ Midwest City High School

a)   Continue fence installation.

b)   Continue turf installation.

c)   Begin installing infill material into turf.

d)   Begin installing retaining wall at West end of track.

e)   Complete installation of security equipment.

 

§ Carl Albert High School

a)   Continue installation of the subsurface drainage system at the practice field.

b)   Continue installation of the rock base at the practice field.

 

 

5/21/10 > Construction Progress May 21, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending May 21, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Continue installing security equipment.  95% complete.

b)   Continued fence installation.

 

§ Midwest City High School

a)   Completed field compaction.

b)   Began installing security equipment.

 

§ Carl Albert High School

a)   Completing the compaction for turf installation.

b)   Began installing security equipment.

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Perform initial punchlist on Monday.

b)   Track striping.

c)   Continue fence installation.

d)   Pour concrete strip on visitor side.

e)   Pour misc. concrete.

f)   Hydromulch.

 

§ Midwest City High School

a)   Begin installation of turf material.

b)   Begin fence installation.

c)   Track striping.

d)   Pour misc. concrete.

 

§ Carl Albert High School

a)   Install asphalt for track on Monday.

b)   Install the subsurface drainage system at the practice field.

c)   Begin installation of the rock base at the practice field.

5/14/10 > Construction Progress May 14, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending May 14, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Due to rain & wet conditions, construction activity was hampered.

b)   Working on final fill dressing.

c)   Continued fence installation.

d)   Terminating cable and installing security equipment.

 

§ Midwest City High School

a)   Continued field compaction.

 

§ Carl Albert High School

a)   Completed sewer line reroute and clean-outs.

b)   Completed the perimeter curbs.

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Continue installing security equipment.

b)   Continue fencing.

c)   Pour concrete strip on visitor side.

d)   Track striping will occur after cure time of surface material

e)   Perform initial punchlist, with weather permitting.

 

§ Midwest City High School

a)   Completing the field compaction.

b)   Begin installation of turf material.

c)   Begin installing fence posts.

d)   Track striping will occur after cure time of surface material.

 

§ Carl Albert High School

a)   Install asphalt for track.

b)   Complete the compaction prep for turf installation.

c)   Install the subsurface drainage system at the practice field.

d)   Begin installation of the rock base at the practice field.

 

5/07/10 > Construction Progress May 7, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending May 7, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Completed turf installation, including all field markings & infill.

b)   Continued fence installation.

 

§ Midwest City High School

a)   Completed track surface installation.  (Striping will occur after cure time of surface material.)

b)   Completed Practice Field, and released to school for use.

 

§ Carl Albert High School

a)   Completed the dirtwork at the practice field.

b)   Poured 50% of perimeter curbs at the practice field.

c)   Completed concrete pour at the pole vault locations.

d)   Completed the track preparation for asphalt.

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Continue fencing.

b)   Begin installation of security cameras & equipment.

c)   Track striping will occur after cure time of surface material.

 

§ Midwest City High School

a)   Begin installation of turf material.

b)   Track striping will occur after cure time of surface material.

 

§ Carl Albert High School

a)   Install asphalt for track.

b)   Complete the compaction prep for turf installation.

c)   Install the subsurface drainage system at the practice field.

d)   Begin installation of the rock base at the practice field.

 

 

4/30/10 > Construction Progress April 30, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending April 30, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   75% complete installing field turf.

b)   Continued installing fence.

c)   Continued landscaping.

 

§ Midwest City High School

a)   Continued installing track surface.

 

§ Carl Albert High School

a)   Stabilized the track sub-surface.

b)   Continued compaction of the rock base on the football field.

c)   Completed 80% of the dirtwork on the practice field.

 

 

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Cut in the yard line numbers & field emblems in turf.

b)   Complete turf installation.

c)   Continue fencing.

d)   Complete landscaping.

 

§ Midwest City High School

a)   Completion track surface installation.

 

§ Carl Albert High School

a)   Install asphalt for track.

b)   Complete the compaction prep for turf installation.

c)   Complete the dirtwork at the practice field.

d)   Install the subsurface drainage system at the practice field.

e)   Begin installation of the rock base at the practice field.

 

4/23/10 > Construction Progress April 23, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending April 23, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Completed field base compaction to prepare for turf installation.

b)   Began turf installation.

c)   Set posts for the 25-second clocks.

d)   Pulled the fiber optic & electric cable for security.

e)   Continued landscaping.

 

§ Midwest City High School

a)   Completed the turf installation at the Practice Field.

b)   Completed the first layer of track surface.

 

§ Carl Albert High School

 

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Continue turf installation.

b)   Continue landscaping.

 

§ Midwest City High School

a)   Continue installing track surfacing.

 

§ Carl Albert High School

a)   Stabilize the track sub-surface.

b)   Begin asphalt paving the track.

c)   Begin dirtwork for practice field.

4/16/10 > Construction Progress April 16, 2010
Mid-Del Public Schools
Synthetic Turfs and Tracks
Carl Albert HS, Del City HS, and Midwest City HS

Construction Progress
Week ending April 16, 2010

Construction activity that occurred this week:

ï‚§ Del City High School
a) Completed track surface.
b) Begin backfill and fine grading of surrounding area.

ï‚§ Midwest City High School
a) 75% complete of turf installation at the Practice Field.
b) Completed grading and landscaping around Practice Field.
c) Track crew mobilized at Rose Field.

ï‚§ Carl Albert High School
a) Completed field base compaction to prepare for turf installation.
b) Prepared subgrade dirtwork for field events.

We are anticipating construction activity for the following items next week:

ï‚§ Del City High School
a) Continue backfill and fine grading of surrounding areas.
b) Complete field base compaction to prepare for turf installation.
c) Begin installing the field turf.

ï‚§ Midwest City High School
a) Complete turf installation at the Practice Field.
b) Grading and Landscaping around track.
c) Begin installation of rubber track surface.

ï‚§ Carl Albert High School
a) Stabilizing the track surface.
b) Begin asphalt paving the track.
c) Begin dirtwork for practice field.
4/09/10 > Construction Progress April 9, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending April 9, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Continued installing track surface - 85% complete.

 

§ Midwest City High School

a)   Completed the security fence at the Practice Field.

b)   Completed preparation for turf at the Practice Field.

 

§ Carl Albert High School

a)   Completed the plastic moisture barrier & drainage rock installation on playing field.

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Complete the track surface.

b)   Continue installing fence.

c)   Landscaping.

 

§ Midwest City High School

a)   Begin installation of turf at the Practice Field.

b)   Grading and Landscaping around track.

c)   Begin installation of rubber track surface.

 

§ Carl Albert High School

a)   Stabilizing the track surface.

b)   Begin asphalt paving on track.

c)   Preparing dirtwork for field events.

d)   Begin dirtwork for practice field.

4/02/10 > Construction Progress April 2, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending April 2, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Started track surface on field events & 25% of track.

b)   Installed goalposts.

c)   Started installing fence.

d)   Started installation of wire & fiber optic cable for security & track timing system.

 

§ Midwest City High School

a)   Completed the asphalt paving.

b)   Started installing fence.

c)   Received bids for the retaining wall at the southwest corner of the playing field.

d)   Started installation of wire & fiber optic cable for security & track timing system.

e)   Practice Field Base compaction for the turf is 85% complete.

 

§ Carl Albert High School

a)   Completed installation of track curbs.

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Continue track surface.

b)   Continue installing fence.

 

§ Midwest City High School

a)   Continue wire & fiber optic installation.

b)   Continue installing fence.

c)   Install security fence at Practice Field.

d)   Grading and landscaping around the track.

e)   Award retaining wall contract.

 

§ Carl Albert High School

a)   Grading of track surface.

b)   Preparing dirtwork for field events.

c)   Begin dirtwork for practice field.

d)   Begin preparations for plastic moisture barrier & drainage rock on playing field.

3/26/10 > Construction Progress March 26, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending March 26th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Poured sidewalks and side strips.

b)   Continued grading & compacting the flex base for the playing field.

c)   Poured the remaining field events.

 

§ Midwest City High School

a)   Poured sidewalks and side strips.

b)   Imported rock & compacted the flex base for the playing & practice fields.

c)   Poured the remaining field events.

d)   Poured goal post base at the practice field.

e)   Completed perimeter drains at the practice field.

f)   Stabilized the track surface.

 

§ Carl Albert High School

a)   Continue installing the exterior track curbs.

 

We are anticipating construction activity for the following items next week:

 

§ Del City High School

a)   Begin installation of final track surface.

b)   Install concrete block wing walls and backfill.

 

§ Midwest City High School

a)   Begin paving the tract.

b)   Complete the drainage rock on playing & practice fields.

c)   Begin the final grading for turf on playing & practice fields.

d)   Receive bids for the retaining wall at the southwest corner of the playing field.

 

§ Carl Albert High School

a)   Complete the track curbs.

b)   Begin stabilizing the track.

c)   Begin preparations for plastic moisture barrier & drainage rock on playing field.

3/19/10 > Construction Progress March 19, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending March 19th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Completed asphalt paving for the track & "D" area.

b)   Installed the flagpoles.

 

§ Midwest City High School

a)   Installed plastic moisture barrier on playing & practice fields.

b)   Began installation of drainage rock on playing & practice fields.

c)   Stabilizing the track surface.

d)   Installed the flagpoles.

e)   Completed the perimeter curbs at the practice field.

f)   Completed field grading at the practice field.

 

§ Carl Albert High School

a)   Completed the perimeter drains on playing field.

b)   Continue installing the exterior track curbs.

c)   Installed the flagpoles.

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Begin install of synthetic turf.

b)   Pour the sidewalks.

 

§ Midwest City High School

a)   Begin paving the tract.

b)   Complete the drainage rock on playing & practice fields.

c)   Begin the final grading for turf on playing & practice fields.

d)   Begin preparations for synthetic turf installation.

 

§ Carl Albert High School

a)   Complete the track curbs.

b)   Begin stabilizing the track.

c)   Begin preparations for plastic moisture barrier & drainage rock on playing field.

 

3/05/10 > Construction Progress March 5, 2010
Mid-Del Public Schools
Synthetic Turfs and Tracks
Carl Albert HS, Del City HS, and Midwest City HS

Construction Progress
Week ending March 5th, 2010

Construction activity that occurred this week:

Del City High School
a) Continued to install rock drainage base on football field.
b) Poured concrete bases for flagpoles.
c) Poured the long jump field event.

Midwest City High School
a) Poured the long jump field event.
b) Poured the pole vault field event.
c) Poured concrete bases for flagpoles.
d) Building and grading track & field sub-base.

Carl Albert High School
a) Set and poured bases for goal posts.
b) Poured concrete bases for flagpoles.
c) Set and poured the echo-drains around the north radius.
d) Began work on the perimeter drains.
e) Began rerouting the new waterline.
f) Completed the sewer line relocation.
g) Continuing to grade track & field.
h) Poured long jump field events.
i) Set and pour track curbs.
j) Continuing Sub-grade dirt on football field.

We are anticipating construction activity for the following items next week, weather permitting:

Del City High School
a) Begin paving track surface.
b) Continue work on field events.

Midwest City High School
a) Completing the field events.
b) Track and Field grading.
c) Stabilizing the track.

Carl Albert High School
a) Complete waterline relocation.
b) Complete perimeter drains.
c) Continue track curbs.
d) Continue Track and Field grading.
e) Continue the sub-grade dirt work on football field.
2/26/10 > Construction Progress February 26, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending Feb. 26th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Conditions too wet; no work completed

b)   Bids were received for the Fencing & Security Cameras

 

§ Midwest City High School

a)   Completed the track curbs.

b)   Installed new waterline.

c)   Completed installation of perimeter drainage system.

d)   Bids were received for the Fencing & Security Cameras

 

§ Carl Albert High School

a)   Beginning work on track events.

b)   Beginning grading on track.

c)   Completed installation of new sewer line.

d)   Bids were received for the Fencing & Security Cameras

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Once ground dries, begin paving track surface.

 

§ Midwest City High School

a)   As field dries, will continue football field grading.

b)   Stabilizing the track.

 

§ Carl Albert High School

a)   Once ground dries, sub grade dirt work to begin on football field.

b)   Installing new water line.

c)   Continue work on field events.

 

 

 

 

2/19/10 > Construction Progress February 19, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending Feb. 19th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Installed new water line relocation.

b)   Stabilized and compacted track base.

c)   Delivering rock base for the football field.

d)   Pulled electrical wire and fiber optic cable to security camera poles.

 

§ Midwest City High School

a)   Completed setting forms and pouring interior track curbs.

b)   Completed installation of echo drains.

c)   Delivering rock for the track base.

d)   Begin relocation of water line.

e)   Imported more dirt fill to the practice field.

 

§ Carl Albert High School

a)   No progress this week.

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Begin paving track surface.

b)   Bids will be received for the Fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

§ Midwest City High School

a)   Continue track curb formwork.

b)   Continuing to excavate & install perimeter drainage system.

c)   As field dries, will continue football field grading.

d)   Continue relocating water line.

e)   Bids will be received for the Fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

§ Carl Albert High School

a)   Once ground dries, sub grade dirt work to begin on football field.

b)   Once ground dries, begin rerouting sewer & water line.

c)   Bids will be received for the Fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

 

 

 

2/12/10 > Construction Progress February 12, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending Feb. 12th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Completed track curbs.

b)   Completed rock base for track.

c)   Fencing & Security Camera pre-bid conference and site visit held.

d)   Installed security camera poles.

 

§ Midwest City High School

a)   Installed security camera poles.

b)   Setting forms and pouring track perimeter curbs.

c)   Delivering rock for the track base.

d)   Fencing & Security Camera pre-bid conference and site visit held.

 

§ Carl Albert High School

a)   Installed security camera poles.

b)   Fencing & Security Camera pre-bid conference and site visit held.

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Rerouting new water line.

b)   Stabilizing and compacting track base.

c)   Delivering rock base for the football field.

d)   Pulling electrical wire and fiber optic cable to security camera poles.

e)   Bids will be received for the Fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

§ Midwest City High School

a)   Continue track curb formwork.

b)   Continuing to excavate & install perimeter drainage system.

c)   As field dries, will continue football field grading.

d)   Pulling electrical wire and fiber optic cable to security camera poles.

e)   Bids will be received for the Fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

§ Carl Albert High School

a)   Once ground dries, sub grade dirt work to begin on football field.

b)   Once ground dries, begin rerouting sewer line.

c)   Pulling electrical wire and fiber optic cable to security camera poles.

d)   Bids will be received for the Fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

2/05/10 > Construction Progress February 5, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending Feb. 5th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Due to extreme weather, little progress achieved.

 

§ Midwest City High School

a)   Due to extreme weather, little progress achieved.

 

§ Carl Albert High School

a)   Due to extreme weather, little progress achieved.

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Begin rock work on the playing field.

b)   A Pre-Bid for the Fencing & Security Cameras will be held Wed., 2/10 @ 10:00 AM.

c)   Bids will be received for the Fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

§ Midwest City High School

a)   Continue curb formwork.

b)   Continuing to excavate & install perimeter drainage system.

c)   A Pre-Bid for the Fencing & Security Cameras will be held Wed., 2/10 @ 10:00 AM.

d)   Bids will be received for the Fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

§ Carl Albert High School

a)   Sub grade dirt work on playing field.

b)   A Pre-Bid for the Fencing & Security Cameras will be held Wed., 2/10 @ 10:00 AM.

c)   Bids will be received for the Fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

 

1/29/10 > Construction Progress January 29, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending Jan. 29th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Continued pouring curbs; near completion.

 

§ Midwest City High School

a)   Continuing to excavate & install perimeter drainage system.

b)   New electrical installed to pressbox location.

c)   Practice field on grade

d)   Beginning work on curb formwork.

 

§ Carl Albert High School

a)   New electrical installed to pressbox location.

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Begin rock work on the playing field.

b)   A Pre-Bid for the Fencing & Security Cameras will be held Wed., 2/10 @ 10:00 AM.

c)   Bids will be received for the fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

§ Midwest City High School

a)   Continue installation of perimeter drainage system.

b)   Continue curb formwork.

c)   A Pre-Bid for the Fencing & Security Cameras will be held Wed., 2/10 @ 10:00 AM.

d)   Bids will be received for the fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

§ Carl Albert High School

a)   Sub grade dirt work on playing field.

b)   A Pre-Bid for the Fencing & Security Cameras will be held Wed., 2/10 @ 10:00 AM.

c)   Bids will be received for the fencing & Security Cameras on Tues., 2/23 @ 10:00 AM.

 

1/08/10 > Construction Progress January 8, 2010

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending Jan. 8th, 2010

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Excavated, set forms and poured curbs

b)   Excavated & set forms for goal posts bases

c)   Poured light & camera pole bases

 

§ Midwest City High School

a)   Excavating for under field drainage system

b)   Poured light & camera pole bases

 

§ Carl Albert High School

a)   Excavation of main field in progress

b)   Primary electric conduit / cabling installed

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Continue curb formwork and pour track curbs.

b)   Continue work on the surface drains

 

§ Midwest City High School

a)   Installing perimeter drainage system.

b)   Beginning work on curb formwork.

 

§ Carl Albert High School

a)   Continue Electrical underground

 

 

 

12/25/09 > Construction Progress December 25, 2009

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending Dec. 25th, 2009

 

Construction activity that occurred this week:

 

§ Del City High School

a)   All East side curbs concrete-in-place

b)   West side curb formwork in progress

c)   Installation of under-field drainage in progress

d)   Waterline installation partially complete

 

§ Midwest City High School

a)   Excavation of main field complete

b)   Removing old drainage system; backfilling and compacting

c)   Practice Field main drainage system installed

 

§ Carl Albert High School

a)   Excavation of main field in progress

b)   Primary electric conduit / cabling installed

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   New light pole bases and electrical work

b)   Continue curb formwork and concrete placement

c)   Continue progress on drainage under the field

d)   Estimate turf installation in late-January 2010.

 

§ Midwest City High School

a)   Preparation to install new underground drainage system

b)   Final field grading

c)   Estimate turf installation on Practice Field in late-January.  

d)   Estimate turf installation on Game Field in mid-February.

 

§ Carl Albert High School

a)   Continue excavating the field

b)   Estimate turf installation on Game Field in late-February.

c)   Estimate turf installation on Practice Field in early-March.

 

12/18/09 > Construction Project December 18, 2009

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending Dec. 18th, 2009

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Electrical work for the two new 25-sec clocks

b)   East side curb formwork

 

§ Midwest City High School

a)   Electrical conduit installed underground

b)   Removed old drainage system; backfilled and compacted

c)   Practice Field sub-grade to level

 

§ Carl Albert High School

a)   Excavating existing top soil

b)   Field grading

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Electrical work for two new light pole bases

b)   Continue curb formwork

c)   Complete drainage under the field

d)   Estimate turf installation in late-January 2010.

 

§ Midwest City High School

a)   Preparation to install new underground drainage system

b)   Prep sub grade

c)   Estimate turf installation on Practice Field in late-January.  

d)   Estimate turf installation on Game Field in mid-February.

 

§ Carl Albert High School

a)   Continue excavating the field

b)   Estimate turf installation on Game Field in late-February.

c)   Estimate turf installation on Practice Field in early-March.

 

 

 

12/11/09 > Construction Project December 11, 2009

Mid-Del Public Schools

Synthetic Turfs and Tracks

Carl Albert HS, Del City HS, and Midwest City HS

 

Construction Progress

Week ending Dec. 11th, 2009

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Stock piled material for drainage installation

b)   Built temporary roadway for access

c)   Removed the goal posts

d)   Installing primary and secondary electrical conduit

e)   Installing conduit for the track timing system

 

§ Midwest City High School

a)   Removed and compacted the existing curbs

b)   Completed grading the field

c)   Hauled the dirt to maintenance

d)   Hauled concrete to disposal

e)   Installing primary and secondary electrical conduit

f)   Removed the goal posts and flagpoles

 

§ Carl Albert High School

a)   Reclaimed the asphalt track

b)   Stripping the sod

c)   Removing the existing curbs

d)   Removed the goal posts and flagpoles

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Installation of track base

b)   Installing drainage under the field

 

§ Midwest City High School

a)   Installing drainage under the field

b)   Continue electrical installation

 

§ Carl Albert High School

a)   Begin field grading

b)   Begin primary and secondary electrical installation

c)   Continuing curb removal and disposal

12/04/09 > Construction Progress December 4, 2009

Construction Progress

Week ending Dec. 4th, 2009

 

Construction activity that occurred this week:

 

§ Del City High School

a)   Reclaimed the track and stabilized

b)   Removed the sod

c)   Graded the field

d)   Demo of curbs & concrete

e)   Demo of abandoned drain pipe

f)   Electrical trenching and installing primary conduit and backfill

 

§ Midwest City High School

a)   Reclaimed the track

b)   Removing excess dirt

c)   Stripped the sod

 

§ Carl Albert High School - Work will continue following 5A Football State Finals 12.5.09

a)   Stripped the track material

 

We are anticipating construction activity for the following items next week, weather permitting:

 

§ Del City High School

a)   Installation of track base

b)   Installing drainage under the field

 

§ Midwest City High School

a)   Grading the track

 

§ Carl Albert High School

a)   Reclaiming the asphalt track

b)   Stripping the sod

c)   Beginning field grading